From Peter CB: 
Hi all,
I went to Shang on Tuesday to prepare and meet the contractor for the Spring/Water restoration.
Summary of Spring Restoration Project
  • I asked the two men to verify that surface run off above the Spring bypassed the Spring effluence and did not contaminate our water source. They crawled through very thick brush and burn rubble to verify that the original waterway is open.
  • Following the pipe, the Spring was uncovered to expose the previous system. I took lots of photos and made notes for them. The project was very successful in cleaning, washing and replacing in kind the previous system.
  • We did add a small cement berm to dam water to fill above the drainpipe and capture Spring water.
  • Additional gravel was added above to “dome” the area.
  • A long fibrous root was pulled from the slotted 1 ¼” PVC pipe that was the problem. The ferns must be kept off the top of the Spring to prevent a reoccurrence.  
So, pipe, gravel, two layers Visqueen 6 mil, gravel, Visqueen, gravel and a cover of larger stone, gravel and even the fire clay bricks which I had not counted on.

I worked on the Pump House plumbing replacing the failed check valve and the fittings both sides of the solar pump. By the 2:00 pm all was done, and valves were opened to flush our piping of silt at sediment tank and line to storage. I also insulated the 1 ½” schedule 80 riser with peal and stick aluminum tape for fire protection. Before I left on Thursday, I closed the valves and started the solar pump, all working fine.

I also got the name of a contractor for the beam repair, so that information will follow when the next phase of this contract is started.
Note: A family member should always be present when a contractor is working. It facilitates questions and gives efficiency to our needs.
It was a productive visit, and I did many other things including my usual meals with Allan and clean up around house and woodshed. New figs are budding along with patio rose. I had two visits from Jake who showed me his video from five wildlife cameras set up on his property.
FYI there is more going on at night than in the day. I saw foxes, bobcats, bucks and several mountain lions.
​
Jake also cleared our upper roads of seven large trees and gave me some pruning loppers and new mouse traps as I had given him one of ours the prior visit. We have a very good neighbor.
See photos and videos below. 
Peter C.B.
P. S.  Adding more photos and video for complete overview of project.  Clearing around the spring should be added to our annual maintenance to prevent future interference. 

Photos & Video

Click on photo for caption description. 

Additional Photos & Video-update

Picture
Picture
Picture
Published on
Image description

Hi All,

Weather was beautiful, warmer Sunday and sunny. (Visit was Jan 4-5)

First thing on the agenda was to look at the spring issue and take pictures for PCBM. Lots of water, just not making it into the pipe.



  


Picture
Overflow of dam is running fine. I'm sure it could benefit from clearing of cattails but at this point they are not obstructing the flow. 
  • Perfect conditions for weeding, so I made great progress on pulling euphorbia and digging out poorly positioned live oak volunteers.
  • Cleaned up area around steps to ramp. Raked around persimmon ++
  • Started new pile for chipper in a place I think will not be in the way.
  • raked oak leaves from path to back gate.
  • cleared ash from fireplace.
  • We emptied incinerator at dump then took it to the lake.
  • Spent a couple hours clearing yellow star thistle and burning it in incinerator. Mowing once the flowers have gone to seed just spreads the seed. This method spreads some seed too but destroys most. Just an experiment. Best method is carefully timed mowing. But that requires recognizing the right conditions and being there to do it. I am not yet comfortable with the idea of driving the mower down there. Too wet now anyway.
The current incinerator has come to the end of its lifespan. Though we do not burn garbage anymore, there are times and conditions where it is good to have one there by the house. 
I have demarcated some small native plants in the area by the lake where we were working on star thistle. These are Foothill Penstemon getting a foothold there and I am hoping to keep them from getting mowed or driven over. Just used materials close at hand...Victor couldn't decipher it, so here are photos to convey my message:
Picture
Picture
Kitchen:
There was evidence of mouse activity on the counter, inside the toaster, inside the stainless containers holding wooden spoons, on the dish drain, under the sink (including amongst the storage containers) and in the window. I cleaned all of these places/things and saw no new evidence the next morning. I think we have never had a mouse on the marble table, so I suggest setting toaster, etc over there overnight and when leaving. Easy enough to do. 
Couldn't find the meat thermometer. 
Down to very little olive oil.

Items needed:
  • 55 gallon drum for incinerator. hopefully a repurposed, inexpensive one. Allan has a special tool to cut the lid off if it is one that doesn't have a removable lid.
  • olive oil
  • meat thermometer

I couldn't find my orange bucket and a short handled lopper I keep up there. The only place I did not check was in the green Jeep, maybe left there from last visit.

There is always more to do up there and we look forward to getting back soon. 
Ingrid and Victor
Published on
​Water is not flowing from the spring. This is not a replenishment issue, as we once thought. The runoff from loose soil after fires, significant amounts of fern growth, etc. has effected the spring development so that it is no longer functional.

We will most likely need to redo the spring and are in the process of getting a quote for the approved spring design, per county building codes.

Much more to come.
Peter CB Madsen